Alwedad Contracting Co. Ltd

Email: alwedad@alwedadsa.com,     Jeddah: +966 12 6914410,     Riyadh: +966 11 2884155

Formula One Circuit Lighting System

Project Summary

The project Located in Jeddah’s stunning Corniche area, approximately 12km north of the city center, the circuit skirts the Red Sea encircles a lagoon and produces spectacular racing under floodlights.eveloped with close collaboration between Tilke GmbH & Co. KG and the Formula 1 Motorsport team led by Ross Brawn.
We have been selected by MUSCO Lighting manufacturer to complete the mission ofinstallation of the LED Lighting System at F1 street Circuit, Jeddah, Saudi Arabia. 

Project Brief:

Client

Ministry of Sport

Main Contractors

M/s. Musco Gulf Lighting and Contracting LLC

Consultants

-

Scope of Project

Formula 1 Circuit Jeddah : Installation of Temporary & Permanent Lighting Poles and LED Lightings for Bridges and Buildings

Project Duration

Three months

Contract value

574,070$

PROJECT DETAILS

The SCOPE include the following:

1. Temporary poles with steel base plates & counterweights.
2. Temporary poles installed on the retaining wall
3. Permanent Poles – Installation of Musco LSS standard poles
4. Lighting system for buildings & bridges. 

1. Temporary poles with steel base plates & counterweights.

The installation of the Musco supplied Poles and fixtures are as following:
a. Marking pole locations & getting client acceptance before proceeding with installation works.
b. Installation of Four Hundred Ninety-Six (496) poles and One Thousand four hundred & Fifty-Eight (1458) lighting fixtures.

2. Temporary poles installed on the retaining wall

The installation of the Musco supplied Poles and fixtures as follows:
a. Marking pole locations & getting client acceptance before proceeding with installation works.
b. Installation of One Hundred Twenty-Three (123) poles and Three Hundred Fifty-Eight (358) lighting fixtures. The contractor should provide all equipment, labor, and materials to distribute, assemble and erect (123) Musco temporary poles including the related control gear, Anchor bolts, templates and the lighting fixtures.

3. Permanent Poles - Installation of Musco LSS standard poles

The supply and installation of all equipment as noted on drawings, including but not limited to:
a. Marking pole’s locations and getting client approval before proceeding with the works.
b. Installation of Eight (8) pre-cast foundations supplied by Musco. The contractor should allow for all materials; equipment; and works necessary to excavate; install; and pour concrete for all the supplied foundations.
c. Allowing for 1.5mx1.5mx1.5m earth pit & ground penetrating radar test to detect any underground services.
d. Assuring the existing underground utilities, manholes and any other obstacles above the ground for equipment access have been located and are clearly marked to avoid damages from construction equipment.
e. Allowing for dewatering mobilization; maintenance; and demobilizing as needed.

4. Lighting system for buildings & bridges.

The installation of the Musco supplied Lighting Equipment and fixtures as follows:
a. Marking mounting locations and getting client approval before proceeding with the works.
b. Installation of One Fifty-Three (153) mounts & Two Hundred Eighty-One (281) lighting fixture.
c. Installation of Eighty (80) Electrical Component Enclosure (ECEs).